Fire Risk Level Increased to High

Fire pits and outdoor fireplaces are permitted, however extreme caution is required for all large open-air burning. Read the full notice here.

4 Sideroad Bridge Replacement


Introduction

Bridge BR-070, located on 4 Sideroad, west of the 7th line and crossing over the East Miniehill Creek, has been identified as requiring replacement as part of routine inspections of the structure. The 2025 Ontario Structure Inspection Manual report gave the structure a bridge condition index (BCI) of 43.22, and replacement is generally recommended at a BCI of 40. The bridge also has an existing load limit of 5 tonnes.

The project includes a review of bridge alternatives, detailed engineering, demolition and replacement of the bridge.

Project Description

This project includes:

  • Review of bridge alternatives
  • Detailed design and engineering
  • Demolition of the existing structure
  • Replacement for the water crossing

Status In Progress

Project Timeline:

October 30, 2027

Anticipated completion 

July 1, 2027

Anticipated start of construction 

December 31, 2026

Anticipated completion of Design 

July 6, 2026

Start of Engineering and Design

Budget

Total budget of $891,850 over two years