Project Overview
The Municipality of Meaford is replacing the bridge on 8 Sideroad (BR-133) to ensure our roads stay safe and reliable. We’re removing the old concrete structure and installing a new prefabricated bridge to maintain service now and in the future.
Project Scope 
This project includes:
-
Full removal of the current concrete bridge
-
Installation of a new prefabricated superstructure
-
All work completed by Cox Construction Limited
Timeline
-
Anticipated project start: September 2, 2025
-
Ongoing end: October 31, 2025 (estimated)
Timelines may be subject to weather and site conditions.
Budget
Total Budgeted: $820,087
Impact on Residents
-
Traffic Disruptions:
-
8 Sideroad is closed at the bridge throughout construction.
-
Please use alternate routes for through traffic.
-
Residents can still access their properties, but do not park on the roadway.
-
-
Noise and Dust:
-
Expect some noise and dust during construction.
-
The contractor is working to minimize both wherever possible.
Project Updates
Updates will be posted here as the project progresses, and future phases will be announced.
Contact Information
For more information about this project, please contact:
Joel Saunders
Project Manager, Infrastructure
Municipality of Meaford