Each year, the Municipality of Meaford invests in improving parts of our road, bridge, facility, and water/wastewater infrastructure. This includes major rehabilitation projects, like this listed below. Find more information here on upcoming and current major capital projects.

Project NameLocationEstimated Start DateEstimate Completion DateBudget
New Meaford Public Library 11 Sykes Street East, Meaford August 2019 October 2020 $5.5 Million total, with $3.5 Million tax supported.
Trowbridge Street Bridge Rehabilitation

Bridge Street between Bayfield Street and Denmark Street

June 15, 2020 November 2020 $1,683,000
Thompson Street

These sections of Thompson Street are scheduled for rehabilitation:

  • Between William Street and Lombard Street
  • Between Nelson Street and Trowbridge Street West
June 1, 2020 October 2020 $1,381,200
Road Resurfacing

These road sections are scheduled for resurfacing:

  • Sideroad 23 from Sydenham-Lakeshore Drive to 6th Concession North
  • Sideroad 33 from Grey Road 15 to 8th Concession North
  • 6th Concession South from Grey Road 18 to Sideroad 6
  • St Vincent/ Sydenham Townline North of Highway 26
  • Old Mail Road from Grey Road 7 to the granular section of road
May 19, 2020 End of August, 2020 $717,000
Bridge 43

7th line near the sideroad 10 intersection

Spring 2020 Fall 2020 $1,339,500
Sykes Street North Reconstruction

Lomabard Street to Commingwood Street

Enigneering and design - 2020

Rehabilitation - 2021 $2,882,200
4th Sideroad

4th Sideroad from 3rd Line to the Meaford/Blue Mountains Townline

May 2020 September 2020 $724,000
Clarifier Rehabilitation

Wastewater Treatment Plant

April 2019 Spring 2020 $1.3 Million