The second phase of this project is taking place mid September, 2024 as part of the Municipality of Meaford's 2024 Capital Projects.  This project will be completed over the course of a three-year contract (2023-2025) with different areas being impacted. Check back to this page for updates. 

The wastewater collection system relining project will will enhance the efficiency and extend the life of our wastewater system by rehabilitating approximately 230 metres of existing wastewater main using non-intrusive, specialized equipment to perform underground work.

Project Description

The wastewater collection system relining project will will enhance the efficiency and extend the life of our wastewater system by rehabilitating approximately 230 metres of existing wastewater main using non-intrusive, specialized equipment to perform underground work.

This project will reduce the cost of the expansion and annual operating costs of the expanded facility by reducing the need for treatment.

Project Timeline

A formal notice will be provided to residents on impacted streets. While work is being completed, impacted sewers will be temporarily out of service for approximately 8 hours. During this time, affected residents are asked to minimize water usage by refraining from taking showers or baths, running dishwashers or laundry machines, and flushing toilets. These measures will reduce the possibility of sewage flows backing up into your home or business.


This project will be completed over the course of a three-year contract with different areas being impacted in 2023, 2024, and 2025. 
Phase 1: Completed August 2023

Phase 2: Beginning September 16, 2024.

Phase 3: To be completed in 2025. Stay tuned for projected lining dates and locations. 

**Please note, projected dates are approximate and weather dependent. All impacted residents will receive notices prior to work being completed.**

2024 Project Maps
Budget
This project was fully funded in 2022 but will be completed as part of the capital project plan in 2023.
This project is being completed over the course of a three-year contract. The anticipated cost for 2023 is $169,330, in 2024 it will be $268,530, and in 2025 it will be $270,000. 
Contact

Cassandra Cesco
Project Manager, Facilities
Municipality of Meaford
21 Trowbridge Street West
519-538-1060 extension 1316 | ccesco@meaford.ca

Neal Tucker
Project Manager
Capital Sewer Services Inc.
905-266-1500 extension 102424

24 Hour Emergency Line: 1-877-536-3002

Resources

phone iconContact Us