Construction Delay on Bakeshop Bridge

Meaford, Ontario – September 12, 2017 – The rehabilitation project for structure 030, otherwise known as Bakeshop Bridge, has experienced delays that have prevented work from continuing.

These delays include 7-10 rain days, as well as the replacement of an aluminum watermain hanger which required specialized fabrication that took over 2 weeks. Another delay was caused by missing thrust blocks behind the concrete abutments, which are now mandatory in any new construction and required engineering and fabrication that took over 3 weeks.

The project is now expected to be completed by late October. A revised project schedule is still being developed between the contractor, engineering consultant and internal project manager.

-30-

For Further Information, Contact:

Darcy Chapman
Treasurer/Director, Financial Services & Infrastructure Management
Municipality of Meaford
21 Trowbridge Street West, Meaford
519 538-1060 ext. 1111 |
dchapman@meaford.ca

FACEBOOK

It seems that module parameters haven't been configured properly. Please make sure that you are using a valid twitter username, and that you have inserted the correct keys. Detailed instructions are written in the module settings page.

Find an Event

Tue Dec 18 @10:00AM -
Holiday Colouring Page
Tue Dec 18 @10:00AM -
Christmas Card Exchange
Tue Dec 18 @10:00AM -
Elf on the Library Shelf
Tue Dec 18 @ 1:00PM -
Euchre