St. Vincent Street Reconstruction


Introduction

This project will include the reconstruction of St. Vincent Street from the Meaford Harbour to Marshall Street East. Engineering and design is to be completed in 2026, with construction scheduled for 2027. The replacement of watermain and sanitary sewer is required to deal with failing, end of life and undersized infrastructure. Additional water and sanitary sewer work in the Harbour will be reviewed as part of the design process to determine the feasibility of an additional bulk water station and sewer dumping station.

Project Description

This project includes:

  • Replacement of watermains from 1936 and 1905
  • Replacement of sanitary sewers that have failed or at a high risk of failure
  • Replacement of stormwater infrastructure and drainage improvements
  • Feasibility of bulk water station and sewer dumping station for the Harbour
  • Possible addition of sidewalks to both sides of the roadway
  • Reconstruction of the paved roadway

Additional Information

Community Information Session

The Municipality of Meaford is hosting an information session on the planned reconstruction of St. Vincent Street from Marshall Street East to Meaford Harbour (Don Bumstead Drive). 

In addition, the Municipality is looking for public feedback on parking options for St. Vincent Street between Marshall Street East and Bridge Street.

Community Information Session

Residents will be able to review plans, ask questions, and learn more about the project.

  • Date: Tuesday, October 27, 2026
  • Time: 4:00 p.m. to 7:00 p.m.
  • Location: Meaford Hall – Terrace Room (12 Nelson Street East, Meaford)

Parking options being reviewed

The municipality is seeking feedback on parking along St. Vincent Street from Marshall Street to Bridge Street and invites you to complete an online survey and share your preferred option. The survey and vote will be available between October 27 and November 27. 

Share your feedback

The online survey will be added to this page on October 13, 2026. Once it is live, residents are encouraged to complete the survey to share their feedback. The survey will remain open until November 27, 2026.

Status In Progress

Project Timeline:

November 30, 2027

Anticipated completion of Construction 

May 1, 2027

Anticipated start of Construction 

December 31, 2026

Completion of Engineering and Design

June 19, 2026

Start of Engineering and Design 

Budget

Total budget of $3,835,740 over two years

Additional Resources

additional-resources

Notice of Commencement

Notice of Community Information Session