This project will include the reconstruction of St. Vincent Street from the Meaford Harbour to Marshall Street East. Engineering and design is to be completed in 2026, with construction scheduled for 2027. The replacement of watermain and sanitary sewer is required to deal with failing, end of life and undersized infrastructure. Additional water and sanitary sewer work in the Harbour will be reviewed as part of the design process to determine the feasibility of an additional bulk water station and sewer dumping station.
This project includes:
The Municipality of Meaford hosted a Community Information Session on October 27, 2026, to share information about the planned reconstruction of St. Vincent Street from Marshall Street East to Meaford Harbour, including early design information and expected construction impacts.
As part of this engagement, the Municipality is also seeking public feedback on parking options for St. Vincent Street between Bridge Street and Marshall Street East. Residents and interested community members are encouraged to review the presentation materials and parking option visuals, then complete the online survey to share their feedback.
Parking Options Being Reviewed
The Municipality is reviewing two parking options for St. Vincent Street between Bridge Street and Marshall Street East. Each option is shown in the visuals below to help residents compare the proposed changes before completing the survey.
Share your feedback
The online survey is now open and will remain available until Friday, November 27, 2026. Survey results will not determine the final recommendation on their own, but will be considered alongside all available information and public comments.
The municipality is seeking feedback on parking along St. Vincent Street from Marshall Street to Bridge Street and invites you to complete an online survey and share your preferred option. The survey and vote will be available between October 27 and November 27.
The online survey will be added to this page on October 27, 2026. Once it is live, residents are encouraged to complete the survey to share their feedback. The survey will remain open until November 27, 2026.
Subscribe to receive email notifications whenever this page is updated. You will be among the first to know about new information, announcements, or changes posted to this page.
Project Manager, Infrastructure
Anticipated completion of Construction
Anticipated start of Construction
Completion of Engineering and Design
Community Information Session
Start of Engineering and Design
Total budget of $3,835,740 over two years