Project Details
Location: 7th Line (300 m south of 157707 7th Line, Meaford).
Anticipated Start Date: October 26, 2026
Estimated Completion: October 30, 2026
Please note that the schedule may change due to weather or other project conditions.
Scope:
This project includes the repair and rehabilitation of the 7th Line:
- Excavation & removal of roughly 50m of roadway
- Geotechnical testing of the sub-base
- Replacement of any unsuitable sub-base materials
- Installation of drainage & erosion controls
- Installation of granular materials
- New asphalt placement
- Site cleanup
Contractor: E.C. King Contracting
Project Impacts
Road Access: 7th Line will be closed from Side Road 10 to Side Road 13 from October 26 to October 30, 2026. Please review the road map below and follow all posted signage and designated detour routes while travelling through the area.
Noise: Residents and property owners should expect some noise during construction hours.
Dust: Residents and property owners should expect dusty conditions during some construction activities however efforts will be made to reduce dust as much as possible.
Vibration: The possibility of vibrations due to compaction equipment during construction is not anticipated to be significant but residents should protect valuables that may be susceptible to damage as a result of vibration.
Property: The Municipality will not be responsible for owner installed items within the road allowance, such as sprinklers, landscaping, lamp posts, etc. If you have any of these items, we recommend that they be removed prior to the project if possible.
Thank you in advance for your co-operation.
Contact
For more information about this project, please visit meaford.ca/7thline.
Roman Mazzocca
Project Manager, Facilities