Fire Risk Level Increased to High

Fire pits and outdoor fireplaces are permitted, however extreme caution is required for all large open-air burning. Read the full notice here.

13 Sideroad Bridge Rehabilitation


Introduction

Structure/Bridge BR-046 is scheduled for rehabilitation to extend the life of the structure and continue service for the municipality.

This bridge is located on 13 Sideroad between Grey Road 12 and 7th Line and crosses over the Bighead River. The concrete structure has been identified through routine inspections as requiring rehabilitation.

Project Description

This project includes:

  • Concrete repairs
  • Repairs to barriers and guiderails
  • Replacement of expansion seals
  • Paving over the bridge and approaches

Additional Information

Impact on Residents 

  • 13 Sideroad will be closed at the bridge throughout construction. Please use alternate routes.
  • Residents can still access their property, but do not park on the roadway.
  • Noise and dusty conditions are expected during construction.

Status In Progress

Project Timeline:

September 4, 2026

Anticipated completion for Construction 

June 15, 2026

Start of Construction 

February 28, 2026

Completion of Engineering and Design 

December 2, 2025

Community Information Session 

July 30, 2025

Start of Engineering and Design 

Budget

Total budget of $894,350